Duration: 16 days
Access roads through wetlands
Creating wetlands
Highway ramp
*Build 3,600 lf access road to wetland
*install culvert pipe
*stabilization fabric
*strip topsoil
*excavation material to create wetland & use for fill on new highway ramp
*haul material over road
NYS DOT Wetland & I-781 Highway Ramp
Duration: 15 days
Demo security canopies
*remove metal canopies for update security project
*metal siding was recycled
*metal structure saved for reuse
Duration: 3 months
site work for new Nice & Easy service station
*cut to fill
*build subgrade for building pad
*sanitary grease trap
*underground storm retainage
*parking lot subbase
*sidewalks
Duration: 6 weeks
C&D landfill expansion & closure
*80,000 cy cut for new cell construction
*waste relocation
*shaping old waste & putting cap on it
*topsoil
*10 acres of erosion control mat
*new cell certified within 1/10 of a foot to design grade
*storm basin for on site retention
Duration: 6 weeks
4 acre cell expansion
4 acre cell closure
*excavated 200,000 cy of dirt and stockpiled it on site
*Moved 55,000 cy of wood debris
*Ground 30,000 cy of wood waste for reuse
*Redesigned and built 2,000 lf of storm drainage
*Rebuilt 1/2 mile of access road
*Maintained dust control
*Gave the owner a recommendation for a redesign for a cost savings. Owner used the redesign and saved them 1 year of airspace.
Adirondack Central School Addition
Cypress Acres Landfill - Ocala, FL (1998)
Our Work
Fort Drum - OP6A Box Culvert
Duration: 4 months
support for gravel pit
*worked at gravel pit digging underwater to load haul trucks to feed 3 screen plants to be stockpilied
Syracuse Sand & Gravel
Duration: 5 days
Demo buildings
*demo 5 buildings & removal
*erosion control
*asphalt removal
*disconnect water, gas & sanitary
*topsoil
*seed & mulch
Fort Drum Fire Station Demo
Duration: 90 days
build 1,500 lf of new taxiway
*topsoil strip, screen and replace
*undercut
*place subbase
*place 2 - 72" storm pipes
*taxiway lighting
*asphalt
*joint filling
*line stripping
*seed & mulch
Hamilton Airport - Phase I - 2011
Duration: 4 months
Co-Gen Plant for Stanley Jones Corporation @ TSCR
*excavation & backfill for foundations & utilities
*installed 24" HDPE chiller lines with a 24" return line
*excavation & backfill for steam lines & expansion loops
*all of these services were installed around live utilities, digging under utilities & pulling new pipes under existing live utilities without interruption
TSCR - 2,500 Car Pre-Cast Parking Garage
Duration: 5 months
5 acre landfill expansion
*Excavated 150,000 cy of dirt and stockpile on site
*20,000 cy of rock excavation
*subgrade preparation for geo-membrane
*Certified subgrade within 1/10 of a foot to design
*Placed 1 foot of drainage sand on top of geo-membrane
*Placed leachate collection sumps, risers, pumpstation, gravity and force main piping
*Relocated 10,000 cy of waste and re-certified slopes (existing cell was overfilled)
*Maintained dust control
Duration: 4 weeks
precast box curlvert
*excavate and set 280 lf of precast box culvert 18' to invert
*excavate and set precast wing walls
Fort Drum Box Culvert 4700
Duration: 8 months
Site work reconstruction
Rebuild baseball & softball fields
Build new soccer field
Replace concrete sidewalks
*irrigation piping
*sodding
*seeding
*clay surface
*flat drain
*J drain
*backstops
*improve drainage
*replace sidewalks
*rebuild baseball & softball fields
*build new soccer field
Stockbridge Valley Schools Addition
Fort Drum Runway 8-26 Runway Rehab
Duration: 2 months
508,000 sf runway rehab
*Place P-209
*fine grade P-209
*paving taxiway
Duration: 7 months
8 acre expansion
Storm System
*Landfill expansion 10' below water level
*Excavated 200,000 cy of dirt and stockpiled it on site
*Certified subgrade within 1/10 of a foot to design
*Excavated 50,000 cy of clay
*Placed 50,000 cy of clay in 6" lifts with 95% compaction, optimum moisture
*Placed 20,000 cy of drainage sand on top of geo-membrane and certified within 1/10 of a foot to design
*Subgrade preparation for geo-membrane
*Placed geo-composite
*Welded HDPE piping
*Installed gradient control piping
*Installed manholes
*Installed lift station
*Built storm ponds, channels and swales
*Placed overflow structures
*Built leachate collection system: pipe, stone and lift station
*Relocated 15,000 cy of waste
*Pumped 4 million gallons of contaminated water
*Re-mediation clean up, oil spill
*Placed rip-rap in storm channels
*Removal of concrete foundations
*Maintain dust control
Duration: 1 week
Emergency Snow Removal
*Winter 2014 - Buffalo Hit with 8' of snow
*Emergency snow removal for Buffalo Bills Stadium
*2 - 12 hours shifts with 2 loaders with snow blow blades
Buffalo Emergency Snow Removal
Duration: 6 months
addition to chapel & parking lot
*clear & grub
*cut & fill parking lot
*install utilities: storm, water & sanitary
*subbase
*sidewalk prep
*screen & replace topsoil
TSCR - Antunyote Golf Course Parking Area & Access Road
TSCR - Co-Gen Plant
This Page is still under construction, thank you!
7 Mile Landfill - Wisconsin
Duration: 4 weeks
site work for commercial building
*site survey
*silt fence
*cut to fill
*subgrade prep
*fabric
*stone subbase
*fine grade
*excavation & backfill footers
*building pad prep
*storm water
*water service
*site electrical
*sidewalk prep
Baldwinsville Family Dollar
Duration: 3 months
Box culvert
*build coffer dams
*dewater
*structure removal
*pier foundations
*pour footers
*set precast
*backfill precast
*build new road section
Duration: 90 days
new 2,500 lf taxiway on active airport
*site survey
*topsoil strip & replace
*cut to fill
*import fill
*storm piping
*subbase
*asphalt paving
*runway stripping
*airport lighting
*airplane tie-down
*seed & mulch
Duration: 140 days
airport new runway & taxiway
widening of existing runway
*185,000 cy of cut to fill
*Box out for new runway & taxiway
*widening existing runway 12' each side
*placing 24" of aggregate stone, 12" P-154, 12" P-209
*fine grade for pavement
*topsoil strip & replace
Canandaigua Airport
Duration: 1.5 years as needed
Golf Dome, Club House & Tennis Dome
*building excavation & backfill for building footers
*all utilities: storm, water, gas & sanitary
*help with electrical & telcom system
*help place fabric for two different dome systems
*rock boring for utilities
TSCR - Golf Dome, Club House & Tennis Dome
Duration: 6 months
8 acre landfill expansion
*Excavated 250,000 cy of dirt and placed it on site
*Certified subgrade within 1/10 of a foot to design
* Subgrade preparation for geo-membrane
*Placed 2' of clay in 6" lifts at 95% compaction at optimum moisture
*Built storm ponds and channels
*Removal of leachate sludge
*Closure and removal of leachate pond
*Built access roads and haul roads
*Restoration of borrow pit
*Built containment wall within the new cell to hold 1.5 million gallons of contaminated water
*Excavated containment wall within new cell back to design grade after contaminated water was removed
*Maintained dust control
Star Ridge Landfill - Alabama
Duration: 3 months
9 acre new cell
*site survey
*topsoil strip & replace
*291,000 cy cut to fill
*385,000 sf fine grade
*36,000 cy soil liner processed
(glacieral til to make 1x10 7 clay liner material)
Ava Landfill
Oneida-Herkimer Solid Waste Authority
Boonville NY
Duration: 90 days
new 2,500 lf runway at new airport
*site survey
*clear & grub
*topsoil strip & replace
*cut to fill
*storm piping
*underdrain
*subbase
*asphalt paving
*asphalt lighting
*electrical vault
*airplane tie-down
*runway stripping
*water service to office
*seed & mulch
Syracuse Suburban Airport
Duration: 1 week
River beautification at transfer station
*clear and grub riverbank
*Subgrade preparation
*Placed rip-rap along riverbank
*Building demolition
King and Queen Landfill - Virginia
Duration: 9 months
site work for child center
*clear & grub
*erosion control/SWPPP
*cut to fill
*building pad prep
*water main, fire loop, sanitary system, gas service
*screen topsoil
*road boring
*play ground prep
*sanitary line 17.5' deep
*topsoil strip & replace
Fort Drum Child Development Center
Fort Drum - Chapel Addition & Parking Lot
Rochester - Ballantyne Road Wetland Mitigation
Duration: 6 months
Central Warehouse Facility
*60,000 cy cut to removal off site
*excavation & backfill building foundation
*storm & fire pond development with liner
*storm utilities
*fire protection line
*sanitary with leach field
*subbase
*paving
Duration: Clean Burning - 1 month
Out Building - 1 month
*Clean burning of tree debris
*Grubbing and deep pit burning with an air curtain
*Working with owner to fit the new out building and comfort station in on an active golf course without interruptions to players
*Out Building site work, septic and pavers
Macon County Landfill - Illinois
Wisconsin River Bank
Duration: 1 year
Extend existing runway & safety improvements
*development of borrow pit
*34 acres of clearing & grubbing
*30,000 cy topsoil strip
*22,000 cy topsoil screen & replace
*4,500 lf haul road development
*550,000 cy borrow to fill
*34,000 cy cut to fill on site
*traffic control
*site survey
*settlement plates
*security fence
*sed-basins
Binghamton Airport Runway Extension & Safety Improvements
Duration: 2 years
site civil C-5 refueling station
*drilling & blasting within 400' of tower
*building excavation & backfill
*storm & sanitary systems
*8"water hydrant, valve & fitting
*gas service
*prep subbase
*concrete curb & gutter
*oil water separator
*prep 5 acres of hard stand for concrete
*topsoil
*seed & mulch
West Virginia C-5 Refueling Station
Gloversville Walmart
Duration: 1 year
Site Package
*rebuild & expand existing live infrastructure at working resort
*removal of parking lots while building new designed parking areas
*expanding water feature pond
*installing storm water under piping
*collection piping up to 42" diameter
*tie-ins to live sanitary lines
*installing new pump station with grinder pumps
*installing new fire and domestic water lines around outside of the new expansion
*rebuilt entrance roads, loop roads while maintaining traffic flow with minor interruption to paying patrons
*new sidewalks & walking paths, some walks were installed with snow melt
*ALL of the excavation & major changes were done with minor interruption to owner's clients
TSCR Site Package
TSCR - Lodge Hotel
Duration: 90 days
Old industrial building site clean up and place green cap on it
*place 18,000 cy of crusher run
*place 610,000 sf of separation fabric
*place 40,000 cy of clean fill
*place 14,000 cy of topsoil
*610,000 sf of seed & mulch
*1,200 lf walking path
Fort Drum Fire Station
TSCR - Shenendoah Parking Area
Duration: 4 months in extreme weather conditions
100 room 5 star hotel
*built 5 star 100 room hotel under extreme weather conditions
*excavated through 3' of frost for deep footers to keep hotel on schedule
*backfilled deep footers with limited access
*built crane pads & access roads
Trent Jones Design 18 hole golf course Burning & Out Building
Pecan Row Landfill - Georgia
Lock E-6
Carrier Industrial Cleanup & Green Space Cap
Duration: 3 months
Parking lot & access road expansion
*55 acres
*clear and grub 10 acres
*66,000 cy topsoil strip
*101,000 cy cut to fill
*746,000 sf subgrade prep
*10,000 lf underdrain
*58,000 ton stone base, placing 5,000 ton per day
*9,000 cy topsoil placed
*developed storm system through sed-basin forbay, rip-rap channel & outlet structures
*planted wetland plants
*1,700,000 sf seed & mulch
*concrete curb (subbed out)
*asphalt paving (subbed out)
*flag poles & rock walls
Duration: 6 months
2,500 car pre-cast parking garage
*excavated & backfilled footers & side walls
*controlled rock blasting was required to get to the depth for footers (some rock cuts were 20' deep)
*Installed footer drains & under floor slab drains
*worked with erection crews to make crane pads and access for precast trucks
Antunyote Golf Course - Fazio Design 18 Hole PGA Golf Course
Duration: 2 years as needed
Site Work Project, school addition
*Building excavation and backfill
*Rebuild parking lot and access road
*Installed sanitary sewer, storm sewer, new manholes, rebuild existing manholes
*Placed 8" water main, hydrants and valves
*Placed topsoil
*Seeded, mulched and maintained for 6 mowings
*Had to run equipment through school to work in courtyard area
*Maintain dust control
Duration: 3 months
5 acre parking apron
750 lf new taxiway
*site survey
*silt fence
*25,000 cy cut to fill
*pavement milling
*infiltration trenches
*20,000 ton P-209 placement compacted to 100%
*asphalt paving
*line stripping
*crack & seat concrete
*storm water system
*24" mat & cradel
*60" Cure In Place Storm Liner
*seeding & mulching
*airport lighting & signs
*airport traffic control
Duration: 90 days
New Hotel site work
*survey
*clearing & grubbing
*topsoil strip & replace
*site cut to fill
*import fill
*building excavation & backfill
*8" sanitary main line
*6" sanitary service line
*8" water main & service
*storm piping & detention pond
*subbase for asphalt
*subbase for sidewalk
*seed & mulch
Duration: 6 months
Pedestrian bridge
*started with excavation of footers and went all the way to doing the finishing wood work with high quality wood finishes.
*We worked with design architect from start to finish
Walmart - Clay
Duration: 12 weeks
Walmart Rehab
Turn old Sam's Club into new Walmart Super Center. Site contractor defaulted. JBS was asked to finish sitework.
*tore out new storm & manholes
*reset manholes, placed new storm pipe
*finished sanitary
*finished water
*finished fire service
*excavated for curb
*prepped sidewalks
*excavated for plumber
*repair damaged utilities
*prepped for pavement
*repair topsoil
*check out site structures & pipe, repaired as needed
*fine graded building slab within 1/4"
Duration: 2 weeks
build new parking lot
*site survey
*pavement prep
*joint filling
*cold milling
*cut to fill
*subbase
*fine grade
*paving
*line stripping
*traffic control
*guide rail
*traffic signs
*seed & mulch
Duration: 7 days per well pad
Create haul roads & drill pads for natural gas drilling
*silt fence & double silt fence with hay bales
*topsoil strip
*clear and grub
*build haul roads
*storm swales
*cut to fill for pads
*cut and line drill ponds
*create drill rig pads
*temporary seed & mulch
Nornew Gas Well Project
Fort Drum MP Battalion
Nice & Easy - Sylvan Beach
Duration: 8 months as needed
Lava Night Club addition
*excavation & backfill for foundations
*utilities: chiller lines, water, fire & sanitary
*sidewalks
*granite curb
*irrigation
*seeding and sodding
TSCR - Lava Night Club
TSCR Pedestrian Bridge
TSCR - Central Warehouse Facility
Duration: 3 months
coal mine reclamation project
*12,500 lf access road built
*3,500 lf straw waddles
*6,000 lf silt fence
*73 acre clear and grub
*1st cut to fill 516,000 cy
*1,200 lf rock lined ditches
*3,200 lf brush barriers
*73 acres seed & mulch
*site survey
Ferndale Coal Mine Reclamation Project
Duration: 4 weeks
build a containment pond for dredging
*52,000 cy cut to fill to make containment dikes to hold material from dredging operation on Erie Canal
*build containment pond for dredging operation
Duration: 3 weeks
Build a berm for dredging operation
*3 acres of clearing & grubbing
*2 acres (8,400 cy) of vegetation removal
*21,000 cy cut to fill on site
*1,700 sf drainage layer
*25,000 sf stabilization fabric
*1,800 sf construction entrance
*98,000 sf seed & mulch
*dewatering
*site survey
Buffalo Berm
Fort Drum Demo
Duration: 12 to 14 days each visit/year
Overburden removal/miscellaneous work
*MSHA trained
*topsoil strip
*remove over burden (30,000 - 100,000 cy)
*build access roads
*rebuild outer safety berms
*precast concrete plant concrete waste clean up
*clean up rock ledges & quarry floors to make safe work areas
*build ramps for radius conveyors
*build 4 acres of sed-basins for stone wash plant
Cypress Acres C&D Landfill (2005)
Duration: 2 months
5 acre landfill cell re-certification
*Cleared debris from drainage sand layer
*Certified drainage sand layer within 1/10 of a foot to design
*Jet cleaned 5,000 lf of existing leachate lines
*Placed 10,000 sy of geo-composite
*Placed 200 ton of stone on existing geo-membrane while maintaining less than 5 psi working load
*Welded HDPE pipe
*Placed 1,000 lf of leachate collection lines on existing geo-membrane
*Tied into live leachate lines
*Closed gap in containment berm and placed geo-membrane to tie into existing geo-membrane
*Dewater (storm dewater)
*Placed 2,000 lf of leachate re-circulation lines
*Placed 3,000 lf of gas collection lines, header lines and valves
*Tied into live gas collection lines
*Maintained dust control
RON Apron - Syracuse International Airport
Duration: 10 months
site work for new fire station
*site survey
*erosion control
*clear & grub
*topsoil strip, screen & replace
*cut to fill
*prep building pad
*water, sanitary, oil water separator, gas service
*asphalt subbase
*sidewalk prep
*seed & mulch
Duration: 4 weeks
wetland mitigation project
build farm fields into wetlands
*erosion control
*strip topsoil
*place cut into stockpiles
*replace stockpiled topsoil
*seed & mulch
*build access roads through wetland
*install drainage pipes across access roads
Duration: 5 months
8 acre landfill expansion
*Excavated 20,000 cy of dirt and stockpiled it off site
*Subgrade preparation for geo-membrane
*Certified subgrade within 2/10 of a foot to design
*Placed 4' of clay in 6" lifts with 90% compaction and optimum moisture
*Dried clay from 45% moisture to 16% optimum moisture
* Welded HDPE pipe
*Placed leachate collection piping
*Contained and by-pass pumped leachate between live cell and new expansion
*Relocated waste
*Tie-in of live leachate gravity pipe
*Maintained dust control
Syracuse International Airport -
Cell Phone Parking
Duration: 1 year
5 acre site package for family clinic
*site survey
*2,000 lf silt fence
*5 acre clear & grub
*5,000 cy topsoil strip
*3,500 cy cut to fill
*750 lf trench blasting for new sanitary on active military base
*56,000 sf subbase
*fine grade
*paving
*storm piping, water service, gas service, fire servce
*traffic control
*seed & mulch
Fort Drum Soldier Family Care Clinic
Duration: 2 years
site work
*Site survey
*Site demo buildings & utilities
*building excavation & backfill
*recycle subbase on site
*topsoil strip and replace
*cut to fill
*storm piping 6" to 48"
*8" water mains, hydrants & fittings
*8" sanitary
*subbase
*sidewalk prep
*concrete hardstand prep
*gas service
*seed & mulch
Duration: 4 months
New parking area, sidewalks, cart path extension, wetland expansion
*development of a private parking area
*clear and grub
*move high voltage electrical service
*redesigned storm system to reroute around existing underground utilities
*development of new wetland and wier
*paving
*granite curb
*sidewalks
*seeding
*help transplant 24" trees
Duration: 4 months
coal mine reclamation project
*280,000 cy cut to fill
*6,500 lf composite filter sock
*33 acres clear & grub
*1,200 lf subsurface drain
*erosion control mat
*33 acres seed & mulch
*site survey
Moshannon Far North Coal Mine Reclamation Project
Duration: 465 days
Site work for new COF/TEMF Buildings
*site survey
*topsoil strip & replace
*cut to fills
*sanitary lines & structures, storm lines & structures, water lines, fire lines
*subbase placement
*drainage & separation fabrics
*fine grade for hardstand
*asphalt parking lots
*sed-basins
*rip-rap channels
*SWPPP infiltration trenches & dry swales
*sidewalk prep
*seed & mulch
Fort Drum COF/TEMF
Hamilton Airport - Phase II (2009)
Duration: 100 days
development of subgrade for a Walmart Store
*44,000 cy topsoil strip
*230,000 cy cut to fill
*3,400 sy geo-wall on 1:1 1/2 slope
*22,000 cy topsoil screen
*15,000 cy topsoil place
Rock Quarries - New York State
Farfield Inn - Verona
Duration: 18 hole golf course - 3 months
Golf course access road - 1 year as needed
Golf Course:
*Clearing & grubbing 70 acres with deep pit burning using an air curtain
*Stripping 100,000 cy of topsoil & stock piling it
*Cut to fill 500,000 cy in 60 days
*Blasting rock to develop a lake feature
*Excavated rock that went to subbase for a new access road to golf course
*Shaping each hole and green, working with designer to make golf course a top PGA golf course
Access Road
*Clearing & grubbing, trying to make the roadway look as natural as possible
*Poor soil conditions we imported shot rock to stabilize subgrade
*10,000 lf of road that is the gateway to a future top PGA golf course